![]() SP 66-645-007 / CSAH 45 Mill, Reclamation, Overlay & Right Turn Lane Addition from CSAH 15 to CSAH 39
A Federal Aid Project that consists of milling, reclaiming, shoulder correction, drain tile installation, vertical profile correction to improve sight distances, right turn lane construction at all public road intersections and bituminous surfacing of the roadway and shoulders to a 10-ton, 36 foot paved roadway.
May 16, 2011 thru June 15, 2011: Complete Intersection Improvements at CSAH 15 and CSAH 39 (Phase I) May 16, 2011 thru July 29, 2011: Mainline Reconditioning, Grading & Paving (Phase II)
Phase I: Detour on CSAH 19, CSAH 21 & CR 53 Phase II (after June 15th): CSAH 15, CSAH 18, CSAH 39, CSAH 18 & 10th Street S.W. Project Open to Local Traffic ONLY