Construction Projects
Rice County Transportation Projects
Scheduled Construction Projects Map
SAP 066-626-013 - Bridge Replacement on CSAH No. 26 (Larson Ave) over N. Fork Zumbro River
- Project awarded to M&K Bridge Construction of Maple Grove, MN in the amount of $459,634.00
- Funded by County State-Aid allotment and State Bridge Bond funds
- Construction anticipated to begin on May 6, 2013 - weather permitting
- Construction time is 60 Working Days (M-F, weather permitting)
- Replacement of the timber bridge structure with a prestressed concrete beam bridge and approach grading/paving
- Traffic impacts: Road/Bridge closure until completion of the project. Detour will be posted.
- Detour Map
- Update #1
SAP 066-623-010 - Bridge Replacement on CSAH No. 23 (Gates Ave) over N. Fork Zumbro River
- Bid opening scheduled for April 18, 2013 at 10:00 am.
- Funded by County State-Aid allotment and State Bridge Bond funds
- Construction anticipated to begin on June 3, 2013 - weather permitting
- Construction time is 15 Working Days (M-F, weather permitting)
- Replacement of the timber bridge with a 2-lines of precast concrete box culvert and approach grading/paving
- Traffic impacts: Road/Culvert closure until completion of the project. Detour will be posted.
- Detour Map
SAP 066-616-016 - Culvert Replacement on CSAH No. 16 (Iona Ave) over Devils Creek
- Project awarded to Rud Excavating of Webster, MN in the amount of $277,338.83
- Funded by County State-Aid allotment and State Bridge Bond funds
- Construction anticipated to begin on July 8, 2013 - weather permitting
- Construction time is 20 Working Days (M-F, weather permitting)
- Replacement of the steel pipe arch culvert with a precast concrete box culvert
- Realignment of the County Road No. 71 intersection with CSAH No. 16
- Traffic impacts: Road/Culvert closure until completion of the project. Detour will be posted.
- Detour Map
SAP 066-626-018 - CSAH No. 26 (Lamb Ave) Pavement Rehabilitation
- Bid opening scheduled for April 23, 013 at 10:00 am
- Funded local bond funds
- Construction anticipated to begin on or after June 10, 2013 and completed by August 24, 2013
- Construction time is 20 Working Days (Monday-Saturday, weather permitting) once construction begins
- Project includes milling, full depth reclamation and bituminous surfacing of CSAH No. 26 from MN TH 60 to MN TH 246
- Traffic Impacts: Minor/Moderate traffic delays associated with construction operations. Flaggers will be used.
SP 066-070-008 - Edgeline Rumble StripEs
- Project awarded to Traffic Marking Service, Inc. in the amount of $96,739.40
- Funded by Federal HSIP funds and County State-Aid allotment
- Construction anticipated to begin on or after June 17, 2013 and completed by August 30, 2013
- Construction time is 20 Working Days (M-F, weather permitting) once construction begins
- Project includes constructing edgeline rumble stripes on: CSAH 1, CSAH 12, CSAH 14, CSAH 15, CSAH 25, CSAH 28, CSAH 36 and CSAH 39
- Project Location Map
- Traffic impacts: Minor traffic delays associated with moving construction operations. Flaggers may be used.
SP 066-070-009 - CSAH No. 38 (Cedar Lake Blvd) Shoulder Paving
- Project awarded to Crane Creek Asphalt in the amount of $214,809.47
- Funded by Federal HSIP funds and County State-Aid allotment
- Construction anticipated to begin on or after July 8, 2013 and completed by August 16, 2013
- Construction time is 15 Working Days (M-F, weather permitting) once construction begins
- Project includes constructing 2-foot paved shoulders and edgeline rumble stripes on the curved segments of CSAH 38
- Traffic impacts: Moderate delays associated with multiple temporary lane closures. Flaggers will be used.
SP 066-070-010 - Ground-In Wet Reflective Pavement Markings
- Project awarded to Century Fence Co. in the amount of $221,308.11
- Funded by Federal HSIP funds, County State-Aid allotment and local levy funds
- Construction anticipated to begin on or after June 10, 2013 and completed by July 12, 2013
- Project includes constructing 37 miles of ground-in wet reflective pavement markings (white edge lines) on: CSAH 1, CSAH 10, CSAH 20, CSAH 27, CSAH 42, CSAH 45 and CR 97.
- Project Location Map
- Traffic impacts: Minor traffic delays associated with moving construction operations. Flaggers may be used.
SAP 066-621-003 - Culvert Replacement on CSAH No. 21 (Cabot Ave)
- Project design in progress.
- Anticipate August/September 2013 construction.
- Funded by County State-Aid allotment and State Bridge Bond funds
- Project includes replacement of the existing concrete box culvert with a precast concrete box culvert
- Traffic Impacts: Road/bridge closure until completion of the project. Detour route will be posted.
SAP 066-627-004 - Bridge Replacement on CSAH No. 27 (Kane Ave)
- Project design in progress.
- Anticipate July 2013 construction.
- Funded by County State-Aid allotment and State Bridge Bond funds
- Project includes replacement of the existing concrete span bridge with a precast concrete box culvert
- Traffic Impacts: Road/bridge closure until completion of the project. Detour route will be posted.
SAP 066-678-001 - Culvert Replacement on CSAH No. 78 (Dundas Blvd) over Rice Creek
- Project design in progress.
- Anticipate August/September 2013 construction.
- Funded by County State-Aid allotment and State Bridge Bond funds
- Project includes replacement of the existing steel arch span pipe with a precast concrete box culvert
- Traffic Impacts: Road/bridge closure until completion of the project. Detour route will be posted.