Rice County Transportation Projects - 2016

 
 
Culvert Replacements & Rehabilitation
  • Project Location:  CSAH No. 8, CSAH No. 11, CSAH No. 23 & CSAH No. 48
  • May – August construction anticipated
  • Funded with local funds
  • Project Includes:  Culvert Replacement or Rehabilitation (Lining)
  • Traffic Impacts:  Daily road closures and traffic delays
 
CSAH No. 46 (Bagley Avenue) - Grading, Pavement Resurfacing, Shoulder Paving
  • Project Location:  CSAH No. 46 between MN TH 21 and CSAH No. 1
  • May – September construction anticipated
  • Funded with Federal-Aid, State-Aid and Local Sales Tax
  • Project Includes: Mill, Reclaim, Grading, Concrete Paving, Concrete Shoulders, Culvert Rehabilitation, Enhanced Pavement Markings, Rumble Strips and Roadside Signage
  • Traffic Impacts:  Road will be closed to thru traffic.  Detours will be posted.
 
CR No. 99 (245th Street West) - Pavement Resurfacing
  • Project Location:  CR No. 99 between the LeSueur County line and MN TH 60
  • June – July construction anticipated
  • Funded with State Park Road Account and Local Sales Tax
  • Project Includes:  Completion of the 2015 project by correcting failed areas and completing final pavement layer.
  • Traffic Impacts:  Minor delays associated with construction operations.  Roadway will remain open during construction.
 
CSAH No. 4 (Independence Avenue) - Turn Lane Construction
  • Project Location:  CSAH No. 4 between 100th St W and Millersburg Blvd
  • July – August construction anticipated
  • Funded with State-Aid and State grant
  • Project Includes:  Milling, Grading, Aggregate Base, Bituminous Surfacing, Pavement Markings and Turf Establishment
  • Traffic Impacts:  Shoulder and single lane closures.  Minor delays associated with construction operations.  Roadway will remain open during construction.
 
Culvert L3923 Replacement on Lamb Avenue (Northfield Township)
  • Project Location:  Lamb Ave, just north of 150th St E
  • August construction anticipated
  • Funded with Town Bridge funds
  • Project Includes:  Culvert Replacement with a Concrete Box Culvert and Approach Grading
  • Traffic Impacts:  Road closure for duration of the project.
 
Culvert L9516 Replacement on Decker Avenue (Bridgewater Township)
  • Project Location:  Decker Avenue over Heath Creek
  • August construction anticipated
  • Funded with Town Bridge funds
  • Project Includes:  Culvert Replacement with Concrete Box Culverts and Approach Grading
  • Traffic Impacts:  Road closure for duration of the project.
 
Culvert L3915 Replacement on CR No. 90 (255th Street East)
  • Project Location:  CR No. 90 between Ibson Ave and Irwin Ave
  • August construction anticipated
  • Funded with State Bridge Bonds and Local Sales Tax
  • Project Includes:  Culvert Replacement with Concrete Box Culvert, Approach Grading and Bituminous Surfacing
  • Traffic Impacts:  Road closure for duration of the project.  Detour route will be posted.
 

2018 CSAH No. 1 Reconstruction (SAP 066-601-020)